Martha’s Vineyard

Regional High School

Building Project

Building Tomorrow Together

"This is incredibly exciting for the island. We want a beautiful building – one that's worthy of all the great things that are happening inside of it. One that students can move through in four years and feel really proud to be part of and come back to. This is the first step."

— Sara Dingledy, Principal

Our Vision

To unite an all-island collaboration focused on a partnership with the Massachusetts School Building Authority (MSBA) that will determine the next steps for the MVRHS campus.

Our School

The regional high school opened in 1959 and has proudly provided outstanding college and workforce preparation and special needs instruction to the Island’s children for a generation. Not surprisingly, the 64 year-old building has become deficient in several areas including space needs and its mechanical systems. Multiple studies and assessments have resulted in the same conclusion and most systems within the school are far beyond their useful lifespan. We believe our school facility can be better and we want to engage in a thorough process that will answer all the community’s questions and unify the island around a preferred option that addresses current concerns and provides a facility that meets the needs of our students well into the future. In March, 2022, we were accepted into the MSBA (Massachusetts School Building Authority) program after 6 years of effort. Participation in this program is a once in a generation opportunity that will guide us on developing the vision for a building project and offers a 38.74% reimbursement for the cost of the project for eligible space. Thanks to our participation in the MSBA program and the advocacy from island stakeholders, voters from all 6 towns approved the district to borrow $2 million to undertake a feasibility study for a building project at annual town meetings in the spring of 2023. With the Island’s support, the school district has created a School Building Committee (SBC) that will provide oversight for the multi-year construction process. The SBC will report to the full High School Committee at each stage of the process.

Our Next Steps

Our participation in the MSBA program is a major first step and gives us a clear path forward with a concrete timeline. There is a long road ahead, and we are in it together. At the end of this process, we have the opportunity to build something great for this island.

PROJECT TIMELINE

  1. MVRHS Timeline

    Feasibility Study

    Define needs, options, costs, and schedule at a high level.

    Feasibility Study
    Winter 24 – Summer 25
  2. MVRHS Timeline

    Schematic Design

    Develop layout, massing, and baseline systems for cost/scope alignment.

    Schematic Design
    Summer 25 – EOY 25
  3. MVRHS Timeline

    Approvals

    Secure agency and stakeholder approvals needed to proceed.

    Approvals
    Winter 26 – Spring 26
  4. MVRHS Timeline

    Vote

    District/community vote on project funding and scope.

    Vote
    Spring 26
  5. MVRHS Timeline

    Design Development & CDs

    Finalize design details and produce permit/bid-ready drawings and specs.

    Design Development & CDs
    Spring 26 – Spring 27
  6. MVRHS Timeline

    Bidding

    Issue documents, receive bids, and award contracts.

    Bidding
    Spring 27
  7. MVRHS Timeline

    Construction

    • New Addition: Summer 27 – Summer 29
    • Renovation, Demo & Site Work: Summer 29 – Spring 30
    Construction
    Summer 27 – Spring 30
  1. Feasibility StudyWinter 24 – Summer 25

    MVRHS Timeline

    Feasibility Study

    Define needs, options, costs, and schedule at a high level.

  2. Schematic DesignSummer 25 – EOY 25

    MVRHS Timeline

    Schematic Design

    Develop layout, massing, and baseline systems for cost/scope alignment.

  3. ApprovalsWinter 26 – Spring 26

    MVRHS Timeline

    Approvals

    Secure agency and stakeholder approvals needed to proceed.

  4. VoteSpring 26

    MVRHS Timeline

    Vote

    District/community vote on project funding and scope.

  5. Design Development & CDsSpring 26 – Spring 27

    MVRHS Timeline

    Design Development & Construction Documents

    Finalize design details and produce permit/bid-ready drawings and specs.

  6. BiddingSpring 27

    MVRHS Timeline

    Bidding

    Issue documents, receive bids, and award contracts.

  7. ConstructionSummer 27 – Spring 30

    MVRHS Timeline

    Construction

    • New Addition: Summer 27 – Summer 29
    • Renovation, Demo & Site Work: Summer 29 – Spring 30