Project Timeline
MVRHS TIMELINE
Feasibility Study
- Winter 24 – Summer 25
Schematic Design
- Summer 25 – EOY 25
Approvals
- Winter 26 – Spring 26
Vote
- Spring 26
Design Development & Construction Documents
- Spring 26 – Spring 27
Bidding
- Spring 27
Construction
- Summer 27 – Spring 30
- New Addition: Summer 27 – Summer 29
- Renovation, Demo & Site Work: Summer 29 – Spring 30